Biện pháp thi công khoan ngầm định hướng ngang HDD

BLOCK B - O Mon Gas Pipeline Project. HDD is a process of installing underground services without trenching is an efficient and professional method widely used in many developed and developing countries.

Ngày đăng: 31-05-2022

713 lượt xem

 BLOCK B - O MON GAS PIPELINE PROJECT
ONSHORE PIPELINE CONSTRUCTION METHODS FOR MAJOR CROSSSINGS

CONTENT OF TABLE

1. PROJECT OVERVIEW
1.1. PURPOSE OF PRESENTATION
1.2. HDD INTRODUCTION

- ONSHORE PIPELINE CROSSING STATISTIC (THONG KE MOT SO CROSSING DAC THU VOI MAT DO GIAO THONG CAO, BE RONG CROSSING LON,…)
- CRITERIA FOR HDD METHOD SELECTION
- TRANSPORTATION LINE FOR ONSHORE PIPELINE CONSTRUCTION
- PROPOSED HDD LOCATIONS
- OPEN CUT METHOD FOR MINOR CANAL CROSSING
- OPEN CUT METHOD FOR MAJOR CANAL CROSSING
- OPEN CUT METHOD FOR MINOR ROAD CROSSING
- THRUST BORING METHOD FOR MINOR ROAD CROSSING
1.3. HDD METHOD
  CONSTRUCTION METHODS COMPARISON
1.4. HDD VIDEO

2. CONCLUSION

1. PROJECT OVERVIEW

Thi công khoan HDD

TRANSPORTATION LINES FOR ONSHORE PIPELINE CONSTRUCTION
Based on approved FS and Site Survey Report, the main transportation lines for onshore construction are as follows:

Sơ đồ hệ thống vị trí thi công khoan hdd
 

PROPOSED HDD LOCATIONS

Bảng vị trí hạng mục thi công HDD

KP 16+100 HIGHWAY 63 AND XANG XEO RO CANAL

Bản đồ kênh Xáng Xẻo Rô thi công khoan HDD

See reference:  Kỹ thuật thi công khoan ngầm

KP30+700 CAI LON RIVER
River width is approx. 580m, deepest depth is approx. 8m. Planned dredging depth is 10m. 

Bản đồ thi công HDD sông cái Lớn

KP36+000 CAI BE RIVER
River width is approx. 87m, deepest depth is approx. 7m. Planned dredging depth is 9.5m. 

Bản đồ thi công khoan HDD sông Cái Bé

KP39+600 HIGHWAY 61
Highway width approx. 9m, high traffic density and approx. 100m from the Go Dat Bridge.

Vị trí cầu Gò Đất

KP58+100 THOT NOT CANAL AND INTERPROVINCIAL ROAD
Canal width is approx. 69m, the deepest depth is approx. 5.2m. Planned dredging depth is 6.5m. This canal runs parallel with an approx. 5m road with medium traffic density. Approx. 70m from the Cay U Bridge 

Kênh Thốt Nốt và đường Quốc lộ

KP82+100 THI DOI CANAL
Canal width is approx. 46m, the deepest is approx. 2.5m. Planned dredging depth is 4m. . (Thêm 1 hình google earth) – bờ song cao, open cut khối lượng đào mở lớn

Vị trí thi công khoan trên bản đồ
 

KP97+200 HIGHWAY 91

Quốc lộ 91

OPEN CUT METHOD FOR SMALLCANALS CROSSING

Step 1: Chặn giao thông 2 đầu kênh, cầu tạm, đường tạm và điều khiển giao thông sang kênh / đường tránh.
Step 2: Excavate the trench as per designed elevation and below the master plan dredging level.
Step 3: Push/ pull the pipe string from construction site through open cut crossing.
Step 4: Lower-in the pipe string and back filling the trench and reinstate bottom of canal.
Step 5: Remove the temporary walls and reinstate canal banks.

Máy khoan định hướng ngang
Máy khoan định hướng ngang HDD

OPEN CUT METHOD FOR OTHER CANALS CROSSING
CANALS WITH MORE THAN 10m WIDE, LESS THAN 3m DEEP AND LOW TRAFFIC DENSITY

Step 1: Mobilize flat barge in to the site. (CậP nhật tương tự slide trên)

Step 2: Excavate the trench and ensure the depth of cover shall be 1m below the master plan dredging level.

Step 3: Lowing the pipeline spool which finish test into trench below bottom canal.

Step 4: Back filling the trench and reinstate bottom of canal.

Khoan HDD

OPEN CUT METHOD FOR SMALL ROAD CROSSING
MINOR ROAD LESS THAN 8m WIDTH AND LOW TRAFFIC DENSITY

Step 1: Prepare construction site and mobilize construction equipment on one half of the road.

Step 2: Temporary bypass road may be built to minimize traffic disruption, if required.

Step 3: Excavate the trench and ensure minimum depth of cover of 1.2m (TOP) reached.

Step 4: Lowering pipe spool which finish test into trench

Step 5: Lowing the pipeline spool which finish test into trench.

Step 6: Back filling the trench and temporary reinstate the road.

Biện pháp thi công khoan HDD 

Xem tham khảo:  Báo giá thi công khoan ngầm

OPEN CUT METHOD FOR SMALL ROAD CROSSING MINOR ROAD LESS THAN 8m WIDTH AND LOW TRAFFIC DENSITY

Step 7: Repeat the procedure on the other half of the road.

Step 8: Tie-in the two spools and hydrostatic test before backfilling the whole trench.

Step 9: Back filling the trench and reinstate the road.

Step 10: Remove the temporary bypass road, if any.
THRUST BORING METHOD FOR MINOR CROSSING
FOR SHORT ROAD CROSSING WITH MEDIUM TO HIGH TRAFFIC DENSITY

Step 1: Excavate two pits on both sides of the road, the size of pits must be large enough to accommodate specialized equipment.

Step 2: Mobilize equipment trust boring equipment in to the pits.

Step 3: Special drill heads will be used to drill the road.

Step 4: Each pipe length shall be welded, NDT and pushed across the bore.

Step 5: Hydrostatic test and backfill the pits.
HORIZONTAL DIRECTIONAL DRILLING (HDD) METHOD
HDD is a process of installing underground services without trenching is an efficient and professional method widely used in many developed and developing countries.
Proven to be faster, more cost effective and definitely less disruptive to surface activities.
HDD systems give people and the environment the convenience and protection of an otherwise polluted and messy worksite.
Suitable for Canals/Rivers more than 20m wide and deeper than 3m with from medium and high traffic density.
HDD METHOD (Con’t)
Step 1: Prepare the working area at Rig site and pipe site
CONSTRUCTION METHODS COMPARISON
Biện pháp thi công khoan hdd
HDD CROSSING COST ESTIMATION

See more: Công nghệ khoan ống ngầm

- Chuyên Tư vấn lập Dự án Đầu tư trên Toàn Quốc.
Thầu thi công Dự án Khoan ngầm trên Toàn Quốc.

- Viết Hồ sơ Môi trường.
+ Giấy phép Môi trường.
+ Báo cáo Công tác bảo vệ Môi trường.
+ Báo cáo Đánh giá tác động Môi trường

Tại sao nên chọn Công ty CP Tư vấn Đầu tư & Thiết kế Xây dựng Minh Phương ?
- Công ty được hình thành trên cơ sở sáng lập viên từng là giám đốc dự án, kỹ sư chuyên ngành xây dựng, công nghệ kỹ thuật, quản trị kinh doanh, từng điều hành các tập đoàn lớn, các Công ty Liên doanh nước ngoài hàng chục năm.
- Với đội ngũ nhân viên đầy nhiệt huyết, năng lực, và giàu kinh nghiệm.
- Là Đơn vị chuyên tư vấn và nhận thầu các dự án đầu tư và thiết kế xây dựng trên Toàn Quốc.
- Tư vấn nhiệt tình, giá cả hợp lí, mang tính cạnh tranh cao.

Quy trình làm việc đảm bảo tiến độ nhanh chóng, hiệu quả cao nhất:
- Chất lượng dịch vụ được khách hàng tin tưởng và ưu tiên đặt khách hàng lên hàng đầu.
- Triển khai thực hiện ngay khi khách hàng kí hợp đồng.
- Đảm bảo đúng tiến độ hoàn thành dự án.

LIÊN HỆ   0903 649 782 

HOTLINE - 0903 649 782

CÔNG TY CỔ PHẦN TƯ VẤN ĐẦU TƯ & THIẾT KẾ XÂY DỰNG MINH PHƯƠNG

 

Địa chỉ: 28B, Mai Thị Lựu, P. Đa Kao, Quận 1, TP.HCM 

Hotline:  0903 649 782 - 028 3514 6426

Email:  nguyenthanhmp156@gmail.com

Website: www.minhphuongcorp.com

Bình luận (0)

Gửi bình luận của bạn

Captcha

FANPAGE

HOTLINE

HOTLINE:
0903 649 782

 nguyenthanhmp156@gmail.com